Construction Milestones 07/26/72 Contract Award 06/04/74 Start structural assembly of Crew Module 08/26/74 Start structural assembly of aft-fuselage 05/23/75 Wings arrive at Palmdale from Grumman 08/24/75 Start of Final Assembly 03/12/76 Completed Final Assembly 09/17/76 Rollout from Palmdale 01/31/77 Overland transport from Palmdale to Edwards 04/10/79 Delivery to Kennedy Space Center Enterprise's Flights: Taxi Tests: 1. 02/15/77 (Max speed 89 Mph) 2. 02/15/77 (Max speed 140 Mph) 3. 02/15/77 (Max speed 157 Mph) Captive-Inactive Flights: 4. 02/18/77 5. 02/22/77 6. 02/25/77 7. 02/28/77 8. 03/02/77 Captive-Active Flights: 09. 06/18/77 10. 06/28/77 11. 07/26/77 Free Flights: 12. 08/12/77 13. 09/13/77 14. 09/23/77 15. 10/12/77 16. 10/26/77